Minuano

Minuano Project

Minuano

Minuano Project


Timeline

  • December 2019
    Award of the lot in the ANEEL transmission auction (02/2019)
  • July 2023
    Obtaining the Installation Environmental License issued by the State Foundation for Environmental Protection (Fepam) of Rio Grande do Sul
  • March 2024
    Obtaining the Operation License for the Caxias Norte Substation
  • September 2024
    Obtaining the Operating License issued by the State Foundation for Environmental Protection (Fepam), of Rio Grande do Sul, for the energization of two transmission lines - sectioning of 525 kV Caixas – Caxias Norte – Itá and the 230 kV Caxias Norte – Caxias 6, which are 35 kilometers long, passing through the municipalities of Caxias do Sul, Flores da Cunha and Farroupilha
  • November 2024
    Energization of the Minuano Project five months ahead of the deadline established by the National Electric Energy Agency (Aneel)


Contact ISA ENERGIA BRASIL

Image of a person smiling, sitting at a table in front of a computer.

Are you interested? Please contact us.
We are available if you have any questions, suggestions or any other topic you want to discuss with us.

Contact us