Timeline
- December 2019
Award of the lot in the ANEEL transmission auction (02/2019) - July 2023
Obtaining the Installation Environmental License issued by the State Foundation for Environmental Protection (Fepam) of Rio Grande do Sul - March 2024
Obtaining the Operation License for the Caxias Norte Substation - September 2024
Obtaining the Operating License issued by the State Foundation for Environmental Protection (Fepam), of Rio Grande do Sul, for the energization of two transmission lines - sectioning of 525 kV Caixas – Caxias Norte – Itá and the 230 kV Caxias Norte – Caxias 6, which are 35 kilometers long, passing through the municipalities of Caxias do Sul, Flores da Cunha and Farroupilha - November 2024
Energization of the Minuano Project five months ahead of the deadline established by the National Electric Energy Agency (Aneel)