The project was built by Aliança Interligação Elétrica (AIE), a consortium between TAESA and ISA ENERGIA BRASIL, with equal participation of 50%. This consortium plays an important role in distributing renewable energy generated in the Northeast—from solar and wind sources—to the Southeast, the region with the highest load consumption.

The project was awarded in Lot 03 of the transmission auction held in 2016.

Location
  • States of Bahia and Minas Gerais
  • Benefited area: connects southern Bahia with Minas Gerais, transmitting wind energy produced in the Northeast to the Southeast
Investment
  • Total: R$ 680 million
  • Allowed Annual Revenue (RAP): R$ 148 million, for the 2023-2024 cycle
  • Jobs created: 2,520 direct and indirect jobs
Operation
  • 546 km of 500 kV transmission lines and 600 towers, interconnecting 14 municipalities in the states of Bahia and Minas Gerais
  • Paraguaçu (BA) - 2,500 MVA of installed capacity
  • 2 substations: Padre Paraíso 2 and Governador Valadares 6

Contact ISA ENERGIA BRASIL

Image of a person smiling, sitting at a table in front of a computer.

Are you interested? Please contact us.
We are available if you have any questions, suggestions or any other topic you want to discuss with us.

Contact us