Timeline
- June 2020
Award of the lot in the ANEEL transmission auction (01/2020) - June 2023
Obtaining the installation environmental license - November 2023
Progress and upcoming interventions of the Riacho Grande Project, currently under construction - April 2024
Foundation Stone Laying Ceremony of the São Caetano do Sul Substation - March 2026
Energization (ANEEL deadline)